推拉篷安装需要留意的顺序

来源:http://www.sdcscp.com/ 日期:2020-12-31 发布人:admin

其一,测量支承结构及联接节点的几何并与描绘值比较,对找形作用进行必要的修正;按修正后的形状进行裁剪描绘,加工制造膜面;如膜面先于支承结构竣工已开始制造,应经过其他结构如沟通联接件等规范等来纠正过失;
First, measure the geometry of the supporting structure and joint, and compare it with the description value, so as to make necessary correction for the shape finding effect; cut and describe according to the corrected shape, and process and manufacture the membrane surface; if the membrane surface is completed before the supporting structure and has started manufacturing, it should be corrected by other structures, such as channeling connectors, etc;
其二,收拾现场,在地上烘托维护材料;向工人阐明工序及分工;翻开膜面,进行如在膜面打孔、穿钢索、设备膜角节点板或膜夹板等准备工作;在支承结构上绑扎绳网以暂时支承翻开的膜面;
Secondly, clean up the site and set off the maintenance materials on the ground; clarify the process and division of labor to the workers; turn over the membrane surface and carry out preparatory work such as punching holes on the membrane surface, threading steel cables, equipment membrane corner gusset plate or membrane splint; bind rope net on the supporting structure to temporarily support the turned over membrane surface;
其三,对边角及有褶皱的区域进行有些张拉调度,并完毕上海膜结构固定膜面及节点;完毕雨水体系设备及防水掩盖等;
Thirdly, some tension scheduling should be carried out in the corner and wrinkled area, and the fixed membrane surface and node of Shanghai membrane structure should be completed; rainwater system equipment and waterproof cover should be completed;
其四,在根底工程或主体结构施工完毕后,进行推拉篷支承结构的设备,并完毕有些补油漆、进行防火处置等
Fourth, after the construction of the foundation project or the main structure is completed, the equipment of the supporting structure of the sliding awning is carried out, and some paint is added and fire prevention treatment is carried out
其五,将加工好的膜制品按施工安排描绘的需求折叠、包装,并做好标明;运送至设备现场;
Fifthly, the processed membrane products shall be folded, packed and marked according to the requirements described in the construction arrangement, and transported to the equipment site;
其六,准备工作安排稳妥后,推拉篷吊装机械就位,吊装并对角点作暂时固定;
After that, the canopy should be lifted and fixed at six points;
其七,逐渐均衡张拉,给推拉篷膜面施加预张力;
Seventh, the tension is gradually balanced, and the pretension is applied to the film surface of the push-pull awning;
其八,清洗表里推拉篷表面。
Eighth, clean the surface of the sliding awning.
以上就是小编为大家整理的推拉篷相关内容,希望可以帮助到大家  更多的精彩内容请关注公司:http://www.sdcscp.com
The above is the related content of push-pull awning organized by Xiaobian for you. I hope it can help you to have more wonderful content. Please pay attention to the company: http://www.sdcscp.com
相关推荐

山东程顺彩蓬厂

皖公网安备 34122502000554号

【本站图片均由网站所有方提供,部分图片来源于网络,如无意中侵犯了某媒体或个人的知识产权,请来信或来电告之,本网站将立即删除。】